2020 worklist
2021
January
Boldt - SDA work continue on 4-10 schedule through February.
February
March
Boldt - Ashland 1 week set up with outage starting on the 8th. Scheduled three weeks of 6-10's for a day and night shift for 6-8 SMALL tube welders.
April
Alma has a four day outage scheduled with contractor and numbers not yet set.
May
PCA Boiler 10, outage for a week only but not yet set. Will have 2 shifts but time and man power not set, pending contract.
June
PCA will have some tank work for one week around the clock. Contract pending.
July
August
September
Nekoosa recovery boiler outage. Starts the 13th and finishes the 22nd. Is currently out for bids!