Menu
header photo

2020 worklist

 

 

 

2021

 

January

Boldt - SDA work continue on 4-10 schedule through February.

 

February

 

March

Boldt - Ashland 1 week set up  with outage starting on the 8th. Scheduled three weeks of 6-10's for a day and night shift for 6-8 SMALL tube welders.

 

April

Alma has a four day outage scheduled with contractor and numbers not yet set.

May

PCA Boiler 10, outage for a week only but not yet set. Will have 2 shifts but time and man power not set, pending contract.

June

PCA will have some tank work for one week around the clock. Contract pending.

 

July

 

August

 

September

Nekoosa recovery boiler outage. Starts the 13th and finishes the 22nd. Is currently out for bids!