Menu
header photo

2020 worklist

 

 

 

2020

January

Fraser shipyard, Bay ship and possibly Marinette, looking for workers for 2-3 months. The schedule is not set yet nor are the hours. We will post as soon as there are concrete number

 

February

Georgia Pacific - #3 boiler install for CRMeyers. Work will start in Mid to late Feb and complete around June. It will be a small crew of 4-6 men and the hours are unknown (40-50).

Excel Energy Ashland - Moorhead  starting on the 17th for 3 men working 5-10's for 2 weeks.

Neenah - Jamar starting the 17th and finishing the 8th. 5-10's for 2 weeks and 1 week of 7-12's. day shift only for 4 men.

 

 

March

Portage - mobilize in on the 9th  and outage starts on the 16th. It will be 6 weeks of 6-10s for a day shift only. estimate of 14  men on the boiler, 6 men on Burner capital work and 4 men on the air heater. There will be a night shift that starts on the 23rd, likely 5-10's for 2 weeks for 15 men (half welders).

Point Beach- starts March 14th for 5 welders on a 6-12 schedule for 4-6 weeks.

Weston - Moorhead - SCR and Boiler work, 12 men on SCR and 4 men on Boiler for 25 days working 5-10's.

Manitowoc Public utilities - Boldt - First half  of the month starting, looking at 10-18 men working likely a 5-10's and a 8 for approximately 3 weeks in duration.

Weston - Moorhead on boiler wall replacement. Starts the 23rd and ends April 23rd, days will have 16 tube welders plus a tool room person and night s will have 14 tube welders and a tool room person. The job will be on 7-12's.

Pulium Plant P31 peaker - Moorhead, starts the 23rd for 3 weeks of 5-10's maybe 6-10s. total of 5 men on a day shift only.

Manitowoc - Unit #8 Boiler starts on the 0th and ends the 17th. 2-4 boilermakers on 6-10's.

Thilmany - #7 Boiler outage starting 16th through 20th. 3 boilermakers for 1 week 5-10's.

 

 

April

Thilmany Kaukauna - #10 boiler preoutage for 4 men starting the 20th through may 1st on 5-10's then starting May 4th through May 22nd, 15 men per shift working 7-12's. Gen Bank change out of 700 tubes.

Fox Energy Center - Moorhead late April for 2 weeks , 10-12 men working 5-10s's.

 

May - 

Stevens Point - power boiler outage for 1 week. No additional information at this time.

UW Oshkosh - State boiler modifications, Moorhead, 4 men on 4-10s for about 4-5 weeks

UW Eau Claire - State Boiler modifications Moorhead, 4 men on 4-10s for 2 weeks

UW LaCrosse - State Boiler modifications Moorhead, 4 men on 4-10s for 4 weeks

Thilmany - Starting the 4th  through the 22nd, digester work for 4 men on 2 shifts working 6-10's.

 

June

Verso Rapids - Jamar, evap maintenance, 2nd through the 9th. 1 week of 7-12's ( 2 shifts, days 12 men and nights 8 men) 

Husky Refinery - expected to start the rebuild, the Contractor, hours and duration are not available at this time. Still working out the details and should know in about two months.

July

 

August

Verso - Wisconsin Rapids, #1 Power Boiler for 1 week outage 21st - 28th, no other information available at this time.

 

September

Verso - Wisconsin Rapids, #3 Power Boiler for 1 week outage  11th -18th, no other information available at this time.

Manitowoc - rear wall replacement possible. 

 

October

Verso - Wisconsin Rapids, #2 Power Boiler for 1 week outage 24th - 30th, no other information available at this time.

 

November - Stevens Point - #4 Power Boiler for 1 week outage 6th - 13th, no other information available at this time.