2017

 

March - 

 Oak Creek, emissions outage

 ERGS, 10th - may 27th bag house

Appleton Coating - 6th  - 10th Boiler #11  inspection 2-3 men 1 week of 5-10's

Appleton Coating - 13th - 17th  Boiler #9  Inspection 2-3 men 1 week of 5-10's

Appleton Coating - 27th - 31st  Boiler #12 inspection 3-4 men of 10's

 

April - 

 P4, 15th -30th emissions work

 Paris Station #3 3rd - May 13th baffles

 Paris Station #4 17th - May 27th baffles

Alma - 24th through May 12th, 28-35 men on days working 6-10's and 4-6 men on nights working 6-10's

Nekoosa - 3rd - 21st - build new tank on 40's for 6-8 men

Mosinee - 24th- 28th Boiler inspection 3-4 men on 1 week of 5-10's

 

May -

P4 catalyst 7th - June 4th

 Valley Plant 8th - June 17th, bag house reroute

Wisconsin Rapids - May 1-5th package boiler for 6 men. Then the 9th through the 21st on recovery boilers.

Wisc. rapids - 8th - 11th 4 men on 10's, then 11th - 20th on evaps 1&2 for 12-16 men on 6-10's.

Wisc. Rapids - 15th - 19th 3-4 men on #6 boiler, 1 week of 5-10's

 

June- 

Oak Creek 20th- may 6th outage

Wisconsin Rapids - power boiler 1, 17th - 25th and power boiler 2, 17th - 25th. men and hours ?

 

July -

 

 

August -

 

 

September -

P4 11th - Nov 18th catalyst

Oak Creek #5 - 4th - Nov 18, boiler outage and maintenance repair

ERGS #2 - 25th - Nov 11 bag house

Concorde Station #1 - 11th - Oct 21 baffles

Concorde Station #2 - 25th - Nov 7  baffles

Appleton Coating - 4th - 13th 10 + men on 10's for unit #10

Rothschild - 11th - 22nd for 10-12 men on 5-10's Boiler work

Rhinelander and Mosinee - 25th -29th set up crews on 40 hours.

 

October - 

Oak creek #6 - 14th - Nov 11th, Boiler maintenance

Nosinee - #14 boiler 2nd - 11th for 10+ men on 12's

Rhibnelander - 2nd - 11th for 10+ men on unit #7 working 12's

 

November - 

 

 

December -