FEBRUARY 2010
21ST THRU LATE MARCH -- 12 TO 15 MEN FOR ONE SHIFT ONLY ( COLUMBIA POWER PLANT )
1ST THRU MARCH -- ESTIMATED 30 MEN PER SHIFT FOR APPROX 9 WEEKS ( P-4 AIRHEATER )
URS/WGI OAK CREEK AS NEEDED ( NEW WORK )
MARCH 2010
1ST THRU 13TH -- OUTAGE FOR 6 MEN ( GREEN BAY )
URS/WGI AS NEEDED ( NEW WORK )
ALMA ONE WEEK OUTAGE UNIT 4
ALMA 2 WEEK OUTAGE UNIT 5
APRIL 2010
17TH THRU SECOND WEEK OF JUNE -- ESTIMATED 30 MEN (GREEN BAY )
1ST THRU MAY - OAK CREEK UNIT 5 DIVISION WALLS DOZEN OR SO MEN
7TH THRU MID JUNE - VALLEY PLANT SUPER HEATER CHANGE OUT, ESTIMATED TOTAL 40 MEN
P-4 CATALYST CHANGE OUT
URS/WGI AS NEEDED ( NEW WORK )
MADGETT 2 WEEK OUTAGE
GENOA 1 WEEK OUTAGE UNIT 3
MAY 2010
URS/WGI AS NEEDED ( NEW WORK )
JUNE 2010
JULY 2010
EDGEWATER STARTING SCR WORK / ESTIMATED TIME FRAME
AUGUST 2010
SEPTEMBER 2010
26TH THRU MID OCTOBER -- OUTAGE WORK FOR ESTIMATED 25 MEN ( GREEN BAY )
1 WEEK OUTAGE UNIT 3 GENOA
OCTOBER 2010
24TH THRU LATE NOVEMBER -- OUTAGE WORK FOR ESTIMATED 50 MEN ( WESTON )
NOVEMBER 2010
28TH THRU MID DECEMBER -- ESTIMATED 20 MEN ON OUTAGE WORK ( WESTON )
DECEMBER 2010