AUGUST 2010
Genoa - nuke plant for 5 men, 3 months 40 hours
Valley plant for D&Z, 4 men on expansion joints for 1 week of 7-10's.
PCA Tomahawk at the end of the month for a short hit. All depends on material delivery.
SEPTEMBER 2010
Late september, 2-3 weeks for about 10 men, hrs ? (WPS)
Genoa - 2 wks for about 6-8 men, hrs ?
Charter street to start demo and bring in package boilers ( Boldt )
Oak Creek, D&Z condensor retube, 30 men for 7-8 weeks of 6-10's.There will also be some airheater work but the manpower and hrs not determined.
Appleton coating just after labor day for 10 days estimating 15 days and 6 nights. (TWEET)
Port Washington for inspections and the manpower will be assigned later. Duration of approximately 3 weeks for inspection.
Thilmany in kaukauna around the 13th for a small job, manpower?
Georgia Pacific around the 13th for a small job, manpower ?
OCTOBER 2010
WPS has 3-4 weeks for 20 men days and 10 men nights
Sheboygan 3 week outage late in the month with Jamar. Same time there will be work with Graycor on some duct work revisions.
Thilmany kaukauna around the 3rd , length and manpower?
Park Falls around the 11th for about a week.
Mosinee papers with Tweet right after the first for about 10 days. estimate 20 days and 10 nights.
Charter street?
November 2010
Sheboygan for Graycor on the prep work for the SCR.
January 2011
Oak Creek unit 6 condensor retube, 6-8 weeks 30 men for 6-10's.
February 2011
WPS 6-8 weeks for about 50 men between two shifts.
Alma about 4 weeks for 6-8 men on multiple maintenance.
Point Beach late month 60 day outage , manpower ?
March 2011
Genoa for about 2 weeks with estimated 6-8 men.
Kewaunee will have 30 day outage for ? manpower.
April 2011
WPS will have two diferent outages estimated at 2 weeks in duration for about 12-15 men per.
Dairyland will have numerous maintenance outages for 6-8 men of about 2 weeks in duration.
*** Capital projects talked about***
Ashland biomass mid 2011
Park Falls biomass late 2011
Air quality controll work dairyland late 2011
Portage air quality control work late 2011- early 2012
WPS air quality control work 2011-2012